Cisco CX-FEIP-2TX= Installation and con?guration Spezifikationen Seite 255

  • Herunterladen
  • Zu meinen Handbüchern hinzufügen
  • Drucken
  • Seite
    / 493
  • Inhaltsverzeichnis
  • LESEZEICHEN
  • Bewertet. / 5. Basierend auf Kundenbewertungen
Seitenansicht 254
6-23
Cisco ONS 15454 Installation and Operations Guide, R3.2
March 2002
Chapter 6 Circuits and Tunnels
Creating DCC Tunnels
Figure 6-16 Selecting DCC tunnel end points
Step 5
Click OK.
Step 6 Put the ports hosting the DCC tunnel in service:
a. Double-click the card hosting the DCC in the shelf graphic or right-click the card on the shelf
graphic and select Open.
b. Click the Provisioning > Line tabs.
c. Under Status, select In Service.
d. Click Apply.
DCC provisioning is now complete for one node. Repeat these steps for all slots/ports that are part of
the DCC tunnel, including any intermediate nodes that will pass traffic from third party equipment. The
procedure is confirmed when the third-party network elements successfully communicate over the
newly-established DCC tunnel.
Seitenansicht 254
1 2 ... 250 251 252 253 254 255 256 257 258 259 260 ... 492 493

Kommentare zu diesen Handbüchern

Keine Kommentare